Provide new LED Battens to replace existing Twin Fluorescent Light Units
Spares and repairs of the existing lighting units deemed no longer cost effective and LED Battens were specified by Surveyor.
The lighting circuits were Twin and Earth Cables laid direct in roof slab, these were to be replaced with a full surface metal conduit installation wired with single core cables.
Consultation with the Asbestos Register found that the School Hall ceilings contained asbestos, All fixing holes for the conduit installation and other building penetrations were carried in conjunction with a specialist asbestos contractor.